project-update 5106
Posted on September 1, 2015 by jrudemiller
Demolition has been completed on the commercial portion of the Central Parkway YMCA project, and load bearing walls are currently being built on the basement level. In addition, plumbers have started under slab rough-ins, and plaster repair in the entry lobby is underway.