May 2020 Updates

4TH & RACE

The structure at 4th & Race stands 11 stories tall, and workers are applying a stone-like finish to the exterior. Inside, mechanical, electrical, and plumbing work is largely complete up to level 6. The final interior stairwell doors have been installed, and exterior masonry work on Race and Elm streets has been finished for the parking garage levels. For additional details, subscribe to regular project updates, and refer to the archive for past updates.

PERSEVERANCE

Crews continue to make progress at Perseverance. At 1505 Vine Street, crews are completing the rebar and finishing up pouring the foundation. Masons will start laying the first courses of masonry for the new build in the coming weeks. At 1511 Vine Street, electrical rough-ins are complete in the basement and on floors one through three. Meanwhile, HVAC rough-in is 90% complete and should be finished this week. Roofing is complete and crews will start hanging drywall in June. Plumbers are making their way through building at 1513-1515 Vine Street with rough-in completed on the basement through second floors. HVAC will move in this week. At 1517 Vine Street, crews have completed wall framing on the second and third floors. The roofing work is now complete.