January 2018 Project Updates

15TH & VINE

The core building at 15th & Vine is on schedule to be completed next month. Construction of the new restaurant is underway, with an anticipated completion date of late March – just in time for Opening Day. Crews are hoping for cooperative weather so they are able to repair and re-open the sidewalks in February. Storefronts have been installed along the first-floor restaurant space, and will be installed in the remaining street-level commercial spaces in the coming weeks. For leasing information on the office and retail spaces, please visit the 3CDC website .

RENNEN & BEECHER FLATS

Grade beams and pile caps are now complete at the site of Rennen and Beecher Flats. At the 1505 Race Street building, crews are currently working on foundation walls and interior utilities. Additionally, framing work is scheduled to begin in the coming weeks.

COURT & WALNUT

Crews continue making great strides at the Court & Walnut project site. The majority of current work remains focused on the basement area, as excavation continues and pile caps are being poured. The pouring and forming of the basement walls is underway, and waterproofing is ongoing. In the coming weeks, crews will begin pouring and forming the basement columns. On the first floor, pile caps and grade beams are also being poured, and crews will begin pouring and forming columns and walls in the coming weeks. For additional details, subscribe to regular project updates, and refer to the archive for past updates.

ABINGTON RACE & PLEASANT

Things are wrapping up at Abington Race & Pleasant as all commercial spaces have received Temporary Certificates of Occupancy (TCO). Excluding 1530-1532 Pleasant Street, all residential units have also received TCOs. Work continues on a few remaining items, in order to obtain full Certificates of Occupancy, which is expected to happen in the coming weeks. Work on the tenant buildout for Elementz, the cultural arts and performance center coming to 33 Green Street, is currently in the framing stage.